56th Street's Rebuild Started at the End Arcadia Expected to Wait

October 29, 2026

On October 12, 2026, the City of Phoenix began construction on the 56th Street bike and pedestrian project. The project covers the roughly 1.5 miles between Thomas Road and Camelback Road, and the City expects to finish it in Fall 2028. The first work is at the south end, between Thomas and Indian School. A few years ago that stretch was scheduled to go second. Because the order flipped, the first months of cones and lane work fall on the blocks around Arcadia Park and Thomas Road. The City lists October 2026 as the start month for both phases but has not posted a work sequence for the north half, where the Camelback Road signal rebuild sits. That signal is the change residents asked for by name.

The order flipped between the plan and the first shovels

An earlier Arcadia News report on the project split it into two pieces. The first was the 0.9 miles from Indian School north to Camelback, at about $14 million. The second was the 0.6 miles from Thomas to Indian School, at about $9 million. The City was hoping to start that northern phase in winter 2025. In December 2023, the Arizona Republic also forecast a 2025 start.

The start came about a year later than those forecasts, and from the other end. On May 20, 2026, the Phoenix City Council took up a contract titled "56th Street: Thomas Road to Indian School Road - Phase 2 Bike and Pedestrian Improvements." The item still describes both phases, with Phase 1 running from Indian School to Camelback. The City's project page lists construction on both phases beginning in October 2026. The October construction notice gets more specific. Work "will initially begin at the south end of the project, focusing on the area between Thomas Road and Indian School Road."

For the next few months, the southern 0.6 miles is where the work is.

What sits inside the first work zone

The south half is short, but a lot of everyday Arcadia sits on it or right next to it.

Stop Address Where it sits on 56th Street
Ranch House Grille 5618 E. Thomas Road South end of the corridor, at Thomas
Arcadia Park 3402 N. 56th St. Inside the first work zone, between Thomas and Indian School
Prince of Peace Lutheran Church and Preschool 3641 N. 56th St. Northeast corner of 56th and Indian School, where the two phases meet
G.R. Herberger Park 5802 E. Indian School Road Just east of the 56th and Indian School intersection
Arizona Falls Arizona Canal, between 56th and 58th streets Reached from the south by a pedestrian footbridge

Arcadia Park is the stop most directly inside the current work area. The City lists a playground, picnic area, restrooms, shade structures and a volleyball court there. The City's standard construction hours are Monday through Friday, 7 a.m. to 4 p.m., with night and weekend work possible "when necessary to minimize impacts to the community." Ranch House Grille serves breakfast and lunch every day from 6 a.m. to 2 p.m., so on weekdays crews and diners share the street from 7 a.m. until closing.

The City says it will issue more notices as specific work activities and traffic changes are scheduled. No lane-by-lane detour plan has been posted yet. For now, the project page and the Arcadia Camelback Mountain Neighborhood Association are the two places to watch. The association reposted the City's construction update on October 16.

The fix residents asked for by name is in the other half

The City says about 330 residents attended three public open houses on the project. One request came up often enough to get its own section on the project page, under the heading "You Asked, We Listened." Residents wanted a left-turn arrow at Camelback Road and 56th Street, both for turning onto 56th from eastbound Camelback and for turning from 56th onto westbound Camelback. The City answered with a complete signal rebuild that includes:

  1. Green, solid yellow, red and flashing yellow arrows for all approaches
  2. A dedicated left-turn lane for northbound 56th Street
  3. Pedestrian push buttons and countdown timers on all four approaches
  4. New ADA ramp access on every corner

Camelback sits at the far north end of the corridor, in the half the construction notice does not list as first. The rebuilt signal is part of the project. The October notice simply doesn't put it in the first stretch of work.

The push for the project came from the neighborhood. The Arcadia Camelback Mountain Neighborhood Association describes support from five nearby schools, two neighborhood organizations, parents and residents. It cites missing sidewalks and bike lanes, speeding, cut-through traffic, unsafe routes to school and stormwater flooding as the problems the project was meant to fix. The City calls it a "community-driven project" in its own notice. When it was presented at the association's annual meeting, District 6 Councilman Kevin Robinson told Arcadia News:

"I'm beyond excited to see the 56th Street project finally moving forward – it's been a long time coming!"

The winning bid came in under the City's own estimate

The council record shows what the project costs now. Three bids came in on March 3, 2026. The City's opinion of probable cost was $26,430,460.50. Hunter Contracting Co. was the low bidder at $23,142,664.40, and Combs Construction Company bid $29,468,633.35. So the winning bid came in about $3.3 million under the City's estimate and about $6.3 million under the next bidder.

The council approved a 10 percent contingency "due to volatile material costs and increased labor prices." That raises the most the contract can pay to $25,456,930.40, and spending above the bid amount needs written sign-off from the Street Transportation Director and the City Engineer. The project uses federal funds, and the contract term is 660 calendar days from the notice to proceed. Counting 660 days from the October 12 start lands in roughly August 2028, close to the City's Fall 2028 target.

The earlier Arcadia News figures add up to about $23 million for both phases together, so the 2026 bid lands almost exactly on that older total. The budget held close to that estimate even as the start moved back a year and the phases swapped order.

What the corridor gets once the cones are gone

Everything above is about the next two years. The finished street is the reason for them, and the City's project details are specific:

  • A 10 to 12 foot multi-use path for younger cyclists, school-age children, families and pedestrians, running continuously along both the west and east sides of 56th Street
  • A 24-inch storm drain from Thomas Road to Camelback Road
  • Low-water-use shade trees next to the sidewalk and path
  • Possible changes to the roundabout at Exeter Boulevard
  • Curb ramps and sidewalks upgraded to current ADA standards
  • Traffic-calming features to slow speeds

The City's 90 percent design roll plots go further for the northern phase. Their Phase 1 legend includes traffic chokers and raised pedestrian crossings, along with raised medians, lighting and improved signals. The construction notice adds signal updates at five intersections and landscaping along the whole corridor. Neither document names the five intersections, and the final design for Exeter has not been published.

The project page also shows three cross-section options: one with no landscape buffer, one with a buffer on one side, and one with buffers on both sides. The City has not said which option goes where. The roll plots and the June 2026 final project map are the documents to open if you want to see your own block.

Keeping your week on track through 2028

The south half is where the work is now, and that's where most of the practical planning applies. Arcadia Park, the Thomas Road end and the approach to Indian School are the stretches to check before a weekday trip. G.R. Herberger Park sits just east of 56th on Indian School. The City lists tennis and pickleball courts, restrooms and a picnic area there. To reach Arizona Falls, SRP describes access from the south over a pedestrian footbridge to a viewing platform on the Arizona Canal between 56th and 58th streets.

For the north half and the Camelback signal, the next City notice is what to watch for. The project page links each new notice as it comes out, and the neighborhood association has been reposting them. Until the City publishes a work schedule for the north half, it hasn't given a date for the new arrows at Camelback and 56th.

If you own a home along 56th Street and want to know how a construction schedule running to Fall 2028 fits into your own timing, Camille Kennard can walk you through it with care and discretion. Start with a free home valuation, and we'll talk through your timing from there.

Work With Camille

Whether you're a first-time home buyer, looking to expand your investment portfolio, or just seeking advice on becoming more financially savvy through real estate, I'm here to help. I believe that with the right knowledge and guidance, everyone can achieve their real estate dreams and create a legacy for their loved ones, Contact Camille today!